Airedale Chemicals

Location

Airedale

MSL's Involvement

MSL were involved with our client during the feasibility stage to review the options of raising the roof of the existing portal frame building by 2.5 meters, whilst the building remains fully operational. MSL completed 10 weeks of site enabling works to the existing structure prior to the installation of the new portal frame rafters and cold rolled purlins. Once the new rafters were installed, MSL had to remove the existing steelwork manually via chain blocks.